Overview

The project involved the install and commissioning of three new water tanks and ancillary equipment to the Newman Water Treatment Plant. The site was located on a sloped area adjacent to the existing plant which coincided with a large earthworks development to create a level pad for the additional tanks. Doolee undertook the civil aspects of this project working closely with Downer and BHP to complete this fast‑tracked project. The project started in February 2024 with completion expected in Q3 2024.

Scope of work

  • Slab demolition
  • Detailed earthworks
  • 16m diameter tank ring beam
  • Various concrete works such as slabs, retaining wall and pedestals
  • Trenching, laying conduit and backfilling for electrical conduits
  • Rock protection

Challenges

  • Fast track programme
  • Working within a live water treatment plant
  • Sloped site with high‑voltage power lines

Highlights

  • Critical path items on track
  • 20000 tonne stone import
  • 3 ring beams excavated, formed, and poured within 10 days

Successful projects start with the right partner

Get in touch with us to discuss how Doolee’s turnkey services can support your operations.

Get in touch

T 1300 620 843E info@doolee.com.au

Doolee excavator and ute on a mine site in front of a rock face